© 2007 Schneider Electric. All Rights Reserved.63230-216-229-B1
Commissioning
Checking Logic Input &
Output Connections
Checking Logic Input Connections
PE50146
Procedure
Proceed as follows for each input:
1 If the input supply voltage is present, use an appropriate electric cord to short-
circuit the contact that delivers logic data to the input.
2 If the input supply voltage is not present, apply a voltage supplied by the DC
voltage generator to the terminal of the contact linked to the chosen input.
Observe polarity and level.
3 Use the Input, output, indicator status screen of the SFT2841 software to
observe the change of status of the input.
4 Press the SFT2841 Reset key as necessary to clear all messages and deactivate
all outputs at the end of the test.
SFT2841: input, output, indicator status
Checking Logic Output Connections
PE50147
Procedure
This test uses the "Output relay test" function from the SFT2841 software in the
Sepam™ Diagnosis screen.
When it is used for the watchdog, only output O5 can be tested.
1 This function requires prior entry of the "Parameter setting" password.
2 Activate each output relay using the buttons in the SFT2841 software. The
activated output relay changes status over a period of 5 seconds.
3 Observe the change of status of the output relay through the operation of the
related switchgear, if it is ready to operate and is powered, or connect a voltmeter
to the terminals of the output contact. The voltage cancels itself out when the
contact closes.
4 At the end of the test, press the SFT2841 Reset key to clear all messages and
deactivate all outputs.
SFT2841: output relay test